One10
Craft DigitalOn Track

03 · Timeline & Progress

Program timeline & platform progress.

All five programs are complete. The platform is 90% complete, with reusable components at 98% and the Site Grid Builder at 75% awaiting testing and feedback.

Programs
Portugal · Jun 14
Complete
Rome · Jun 21
Complete
Ritz Cruise · Jun 22
Complete
Costa Rica · Aug 11
Complete
Cabo · Aug 24
Complete
Jun
Jul
Aug
Sep
Portugal
Rome
Ritz Cruise
Costa Rica
Cabo

Platform Milestones

Foundation → Reusable Framework → Testing
Project Kickoff
Started
100%
Jun 1, 2026
Foundation
Complete
100%
Jun 5, 2026
Platform Architecture
Complete
100%
Jun 10, 2026
Portugal Deployment
Complete
100%
Jun 14, 2026
Rome Multi-Program Deployment
Complete
100%
Jun 21, 2026
Ritz Cruise Deployment
Complete
100%
Jun 22, 2026
Reusable Components
Refining from One10 feedback
98%
Sep 2026
Mobile First Redesign
Complete
100%
Aug 11, 2026
Costa Rica Build
Completed
100%
Aug 11, 2026
Cabo Build
Complete
100%
Aug 24, 2026
Platform Complete · Testing & Training
Final testing & training
90%
Sep 2026
Site Grid Builder
Awaiting testing & feedback
75%
Sep 2026